In one sentence: Consultation is required for qualifying works costing any one leaseholder more than £250, and for qualifying long-term agreements (over 12 months) costing any one leaseholder more than £100 in a 12-month accounting period (reg 6; reg 4).
Last reviewed · Primary source: Landlord and Tenant Act 1985, s 20 · all sources
Updated · 8 min read
If your landlord in England or Wales plans major works or a long-term contract that will cost you more than a set amount, it must consult you first under section 20 of the Landlord and Tenant Act 1985. If it does not consult properly, and the tribunal does not excuse it, what it can recover from each leaseholder is capped at £250 for works and £100 a year for long-term agreements (s 20; reg 6; reg 4). This guide walks through the stages, the deadlines and what you can do at each one.
Update, 20 November 2026: On 19 November 2026 the Government said it will raise the section 20 thresholds in England to £500 per leaseholder for qualifying works and £200 a year for long-term agreements, legislate through the Commonhold and Leasehold Reform Bill to overturn the effect of Daejan v Benson and restrict the grounds for dispensation, introduce standard forms and a deadline for works to begin, and let leaseholders opt out of consultation if the majority agree (GOV.UK). These changes are not law yet; the current thresholds and the Daejan test below still apply. Read our report on mandatory reserve funds and the section 20 changes.
When consultation is required
Section 20 limits a leaseholder’s contribution to qualifying works or a qualifying long-term agreement (QLTA) unless the consultation requirements have been complied with or the tribunal has dispensed with them (s 20(1)). “Qualifying works” are works on a building or other premises; a QLTA is an agreement entered into by or on behalf of the landlord for a term of more than 12 months (s 20ZA(2)).
The thresholds come from the Service Charges (Consultation Requirements) (England) Regulations 2003:
- Works: consultation applies if the works would make any tenant’s contribution more than £250 (reg 6).
- Long-term agreements: consultation applies if any tenant’s contribution under the agreement would be more than £100 in any accounting period of 12 months (reg 4).
The test looks at the most any single leaseholder will pay, not the average, and the Leasehold Advisory Service (LEASE) notes the £250 figure includes VAT (LEASE). So in a block where shares differ, the leaseholder with the largest share decides whether consultation is needed. Examples of typical qualifying works are roof replacement, external redecoration or lift renewal.
The three stages for ordinary major works
Which procedure applies depends on whether the works are under an existing long-term agreement and whether public notice is required (reg 7). The most common case, qualifying works not under a QLTA, follows Part 2 of Schedule 4 to the 2003 Regulations (Sch 4 Pt 2).
Stage 1: Notice of intention
The landlord must give written notice to each leaseholder and to any recognised tenants’ association. The notice must describe the proposed works in general terms (or say where and when the description can be inspected), state why the landlord considers the works necessary, invite written observations, and invite leaseholders to nominate a contractor from whom the landlord should try to obtain an estimate. Observations and nominations must be sent within the relevant period, which is 30 days beginning with the date of the notice (reg 2). Inspection must be free, and if no copying facilities are offered, the landlord must provide a free copy on request. The landlord must have regard to any observations it receives.
LEASE points out that the tribunal has treated the “date of the notice” for a posted notice as usually two working days after posting, so keep the envelope and note when it arrived (LEASE).
Stage 2: Statement of estimates
The landlord must then try to obtain estimates, including one from a contractor nominated by leaseholders. It must supply a statement setting out at least two estimates for the works and a summary of the observations received at Stage 1 with its responses. The rules require that:
- at least one of the estimates is from a person wholly unconnected with the landlord (the Schedule defines connection, for example where the contractor is a director or manager of the landlord company, or a close relative of one);
- where an estimate was obtained from a leaseholders’ nominee, it is included in the statement;
- all the estimates are made available for inspection;
- leaseholders are invited to make written observations on the estimates within a further 30-day relevant period (Sch 4 Pt 2, para 4).
The landlord must again have regard to the observations. This is usually the most useful stage for leaseholders: compare the specifications behind each estimate, ask whether the cheapest bid covers the same scope, and check the connection rules.
Stage 3: Notice of reasons for the award
Within 21 days of entering into the contract, the landlord must give a notice stating its reasons for awarding the contract (or saying where they can be inspected) and summarising any observations on the estimates with its responses. This notice is not needed if the contract went to a leaseholders’ nominee or to the person who submitted the lowest estimate (Sch 4 Pt 2, para 6).
Long-term agreements and works under them
Different schedules apply to long-term agreements themselves, for example a multi-year cleaning or maintenance contract, and to works carried out under an existing QLTA (reg 7). LEASE explains that for works under a long-term agreement there is only one stage, because the contractor has already been chosen; leaseholders still receive a notice describing the works and inviting observations (LEASE).
Dispensation: when the landlord skips or botches consultation
A landlord that has not consulted, or has made mistakes, can apply to the tribunal for dispensation. The tribunal may dispense with all or any of the requirements “if satisfied that it is reasonable” to do so (s 20ZA(1)). Applications can be made before or after the works, for example where an urgent roof leak cannot wait for a three-month process.
In Daejan Investments Ltd v Benson [2013] UKSC 14, the Supreme Court held that the main question is whether the leaseholders suffered relevant prejudice because of the failure, such as paying for inappropriate works or paying more than they should. Leaseholders must identify a credible case of prejudice, and the landlord must then rebut it. The tribunal can grant dispensation on terms, for example a reduction in the recoverable cost or payment of the leaseholders’ reasonable costs of the application (UK Supreme Court). In England the application is made on GOV.UK form Leasehold 5 (“dispensation from consultation requirements”) to the First-tier Tribunal (Property Chamber) (GOV.UK forms).
England and Wales
Section 20 applies in both countries, but the detailed procedure comes from separate regulations. In Wales it is the Service Charges (Consultation Requirements) (Wales) Regulations 2004, which also set the works threshold at more than £250 (SI 2004/684, reg 6). Welsh disputes go to the Residential Property Tribunal Wales rather than the First-tier Tribunal. If you are in Wales, check the Welsh regulations before relying on the English paragraph numbers above. Scotland has no section 20 equivalent; owners there deal with registered property factors under a statutory code, covered in our guide to Scottish property factors.
A checklist for leaseholders
- Diarise the 30-day deadline from the date of each notice and respond in writing before it ends.
- Ask to inspect the specification and any surveyor’s report behind the works.
- Nominate a contractor at Stage 1 if you know a reputable firm; the landlord must try to get an estimate from a nominee.
- At Stage 2, check that at least one estimate is from an unconnected contractor and that like is compared with like.
- Keep copies of every notice, envelope and reply. If consultation was skipped, you can raise the £250 cap when the bill arrives, and the landlord will need dispensation to recover more.
- If you think the cost itself is unreasonable, that is a separate question under section 19, decided by the tribunal under section 27A (s 19; s 27A).
For the reasonableness test, the 18-month rule and how to apply to the tribunal, see our guide to challenging a service charge in England and Wales.
Looking ahead, the Leasehold and Freehold Reform Act 2024 will change how service charges are demanded and reported in England, but it does not replace section 20 consultation (2024 Act, Part 4). We track the dates in service charge transparency under the 2024 Act.
How much do major works have to cost before my landlord must consult?
More than £250 for any one leaseholder, including VAT. For long-term agreements the threshold is more than £100 per leaseholder in any 12-month accounting period.
How long do I have to respond to a section 20 notice?
30 days beginning with the date of the notice (regulation 2 of the 2003 Regulations). If the notice was posted, the tribunal usually treats its date as two working days after posting.
What happens if my landlord did not consult?
Unless the tribunal grants dispensation, the landlord can recover no more than £250 from each leaseholder for the works (or £100 a year for a long-term agreement).
Can a landlord get dispensation after the works are done?
Yes. The tribunal can dispense if it is reasonable. Following Daejan v Benson, it focuses on whether leaseholders suffered real prejudice and can attach conditions.
Does section 20 apply in Wales?
Yes, under the Service Charges (Consultation Requirements) (Wales) Regulations 2004, with the same £250 works threshold.
General information, not legal advice. Last updated: 20 November 2026. How we check facts: Editorial Standards.
Sources
- Landlord and Tenant Act 1985, s 20 (legislation.gov.uk)
- Landlord and Tenant Act 1985, s 20ZA (legislation.gov.uk)
- SI 2003/1987, reg 2 (relevant period) (legislation.gov.uk)
- SI 2003/1987, reg 4 (£100 QLTA threshold) (legislation.gov.uk)
- SI 2003/1987, reg 6 (£250 works threshold) (legislation.gov.uk)
- SI 2003/1987, reg 7 (legislation.gov.uk)
- SI 2003/1987, Schedule 4 Part 2 (legislation.gov.uk)
- SI 2004/684 (Wales), reg 6 (legislation.gov.uk)
- Daejan Investments Ltd v Benson [2013] UKSC 14 (supremecourt.uk)
- GOV.UK: Leasehold management dispute application forms (gov.uk)
- LEASE: Responding to a Section 20 consultation (lease-advice.org)
- MHCLG, “Government response to the Strengthening leaseholder protections over charges and services consultation: further service charge measures”, 19 November 2026 (gov.uk)